Caution&#58 King Kong Project Continues

Where will Kong be the week of May 10?

The King Kong Project will continue with the installation of the new 12 inch water main along West Plummer working east to Daugherty. Beginning Tuesday, May 11 crews will expand the work and begin at South Daugherty and West Plummer and head west to Ammerman along Plummer. Traffic in this area should expect one block street closures to thru traffic.

Bore crews will continue with their work along West Plummer.

Along South Seaman crews will continue with the kill outs of the old water mains as well as continuing with tie-ins at cross streets. Crews will begin tie overs in the 1000 block as well.

Pot Holing will begin on South Marsh between Foch and Conner.

Please remember when travelling in these construction areas to be on the alert and watch for crew members as well as heavy equipment.

For questions or comments please contact Eastland City Hall at 629-3349.